Footbridge Toolkit

ArcelorMittal – All Regions

  • The footbridge toolkit provides an integration of products and services, establishing an ecosystem in the production chain.
  • The economic impact is reduced by up to 25% (comparing with baseline solutions) and the time and physical space for interventions are reduced, mitigating / eliminating risks for the team and third parties.

Characteristics

Activities (and products) carried out to reduce the total erection time :

  • Step #1 | Foundation – Use pre-assembled welded rebars with steel permanent formwork
  • Step #2 | Mesostructure – Use of precast columns
  • Step #3 | Ramps – Composite structure (steel deck and steel beams – built-up sections)
  • Step #4 | Footbridge – Composite structure (steel deck and truss / steel beams – cellular or angelina beams)

Applications

  1. Valparaíso de Goiás (GO) – 1 footbridge 2023
  2. Ribeirão das Neves (MG) – 1 footbridge2023
  3. Sinop (MT) – 1 footbridge 2023
  4. Espírito Santo – 8 footbridges 2023
  5. Marília (SP) – 2 footbridges (on-going) 2023
  6. Oriente (SP) – 1 footbridge (on-going) 2023
  7. Assis (1) – 1 footbridges (on -going) 2023